How to win a public tender in the UK: a step-by-step guide

Procurement Act 2023, Find a Tender, thresholds, procedures, award and standstill: how public procurement works in the UK and how to bid, step by step.

The Explain team

noviembre 24, 2026

7 min

How to win a public tender in the UK: a step-by-step guide

In short: since 24 February 2025, public procurement in England, Wales and Northern Ireland has been governed by the Procurement Act 2023. Opportunities covered by the Act are published on Find a Tender, suppliers register once on that platform, and contracts are awarded to the "most advantageous tender". This guide walks you through the process, from finding a tender to signing the contract.

Which rules apply to your tender?

The first question is not how to write your bid, but which regime applies. Three regimes currently coexist in the UK.

  • The Procurement Act 2023 applies to procurements started on or after 24 February 2025 by contracting authorities in England, Wales and Northern Ireland, and by UK-wide bodies. It replaced the Public Contracts Regulations 2015 and the other EU-derived regulations.
  • The old regime still governs procurements that began before 24 February 2025. Contracts awarded under those rules, including frameworks, keep running under them, sometimes for years.
  • Scotland has its own legislation for devolved Scottish authorities (the Procurement Reform (Scotland) Act 2014 and the Public Contracts (Scotland) Regulations 2015), with its own portal, Public Contracts Scotland.

Wales applies the Procurement Act together with its own Welsh regulations and policy notes. In practice, the tender notice and documents always state the legal basis: read it before anything else.

Thresholds: when the full rules apply

The Act's full set of obligations applies to "covered procurements", meaning contracts above the thresholds. From 1 January 2026, the main thresholds, which include VAT, are:

  • £135,018 for goods and services bought by central government authorities;
  • £207,720 for goods and services bought by sub-central authorities, such as local councils;
  • £5,193,000 for works contracts.

Below these amounts, lighter rules apply, but transparency obligations remain: if an authority advertises a contract worth £12,000 or more (central government) or £30,000 or more (other authorities), it must first publish a below-threshold tender notice on Find a Tender, and it must publish the contract details once the contract is signed. Thresholds are revised every two years, so always check the current figures on GOV.UK.

Step 1: register on Find a Tender

Find a Tender is the central digital platform provided for by the Act: an enhanced version of the service, launched on 24 February 2025. Contracting authorities covered by the Act publish their notices there, from pipeline and tender notices to contract award and contract performance information. It is free: you should never pay to see public sector opportunities.

To bid for a covered procurement, your organisation must register on the platform and complete its core supplier information: legal identity, connected persons, financial information and any exclusion grounds. You then get a unique identifier that buyers use in their notices. The information is entered once and shared with each buyer you bid to, so keep it up to date.

Many authorities also run their tenders through their own e-tendering portal. The notice will tell you where the tender documents are and where to submit.

Step 2: watch the market early

The Act puts more information in the public domain before the tender itself. Two notices are worth watching:

  • Pipeline notices: authorities that expect to spend more than £100 million in the coming financial year must publish, within 56 days of its start, the procurements above £2 million they plan to launch over the next 18 months.
  • Preliminary market engagement notices: they announce that a buyer is consulting the market before finalising its approach. Taking part is a chance to understand the need and, sometimes, to shape a realistic specification.

Set up alerts on Find a Tender by keyword and category, and track the authorities you target. The suppliers that win most often rarely discover the tender on the day it is published.

Step 3: understand the procedure

The Act reduces the number of procedures to two competitive ones:

  • The open procedure: a single stage, open to every interested supplier, who submits a full tender.
  • The competitive flexible procedure: the authority designs its own process, which can include a selection stage, several rounds of tenders, negotiation or presentations. The steps are described in the tender notice and documents, and award criteria can only be refined if the documents announced that possibility.

Contracts can also be awarded through frameworks (including "open frameworks" that are periodically reopened to new suppliers) and dynamic markets, which replace the old dynamic purchasing systems. Direct award without competition remains possible only in limited cases defined by the Act.

Step 4: clear the exclusion checks and meet the conditions of participation

Before your tender is assessed, the authority checks that you can be trusted with the contract.

  • Exclusion grounds. The Act lists mandatory and discretionary grounds, from certain offences to poor past performance, and also covers your "connected persons" and, where relevant, your subcontractors. A central debarment list records suppliers that a minister has found to be excluded or excludable. If an issue concerns you, explain the self-cleaning measures you have taken: the authority must consider whether the circumstances are likely to occur again.
  • Conditions of participation. These assess your legal and financial capacity and your technical ability: turnover, insurance, relevant experience, qualifications. They are usually covered in a Procurement Specific Questionnaire (PSQ), which complements the core information already held on Find a Tender.

Step 5: write a tender that scores

Under the Act, contracts are awarded to the most advantageous tender, assessed against award criteria published in advance, with their weightings. Price matters, but in most service and works tenders quality carries a large share of the marks.

The quality part is made of questions, each with a weighting, a scoring scale and often a word or page limit. Evaluators score each answer against the published criteria, usually independently, then agree a moderated score. Three habits make the difference:

  • answer the question asked, in the order asked, using the buyer's words;
  • back every claim with evidence: named people, methods, past contracts, figures;
  • make the response specific to this contract, this site, this service.

In above-threshold procurements run by central government departments, their executive agencies and non-departmental public bodies, social value currently carries a minimum weighting of 10% of the total score under PPN 002, and the commitments you make become contract terms. For procurements launched from 1 January 2027, PPN 026 sets a minimum of 10% for contracts between £1 million and £5 million and 20% for contracts of £5 million or more. Other authorities may adopt the same approach. We cover quality writing in detail in our guide How to write quality responses that score in UK public tenders.

Step 6: after submission, award and standstill

Once tenders are assessed, the authority sends each supplier whose tender was assessed an assessment summary, explaining how its tender scored against each criterion and, for unsuccessful bidders, how it compared with the winner. Read it carefully, even when you win: it is the best feedback you will get for the next bid.

The authority then publishes a contract award notice, which in most cases opens a standstill period of at least 8 working days before the contract can be signed. There is no mandatory standstill for call-offs under frameworks, contracts awarded through dynamic markets, light touch contracts or urgent direct awards. If you believe the rules were breached, this is the window to act: if you start proceedings during the standstill period and notify the authority within that period, the authority cannot enter into the contract until the court lifts the suspension.

Step 7: deliver, because performance is now public

The Act extends transparency into contract management. For most contracts above £5 million, authorities must set at least three key performance indicators, publish them and assess performance against them at least once a year. Frameworks, concession contracts and light touch contracts are exempt, and an authority can also decide that KPIs are not an appropriate way to assess performance. Poor performance can be published and, in serious cases, become a ground for exclusion from future procurements. Delivering well is now part of your next bid.

Bidding from abroad

A supplier based in the EU or elsewhere can bid for UK public contracts. Registration on Find a Tender is open to non-UK organisations, which can register with a non-UK address. If your organisation has no identifier from one of the registers the platform recognises, such as Companies House, the platform generates a unique identifier for you. Check two points early: whether the contract is covered by an international agreement that gives your country access to UK procurement, and whether the buyer requires a UK presence, insurance or security clearance for delivery.

Checklist before you bid

  1. Check the legal regime in the notice: Procurement Act, old rules or Scottish rules.
  2. Register on Find a Tender and keep your core supplier information up to date.
  3. Read every document: specification, award criteria, weightings, scoring scales, word limits, contract terms.
  4. Check the exclusion grounds and conditions of participation before investing in the response.
  5. Plan your quality answers question by question, with evidence for each claim.
  6. Note the clarification deadline and the submission deadline on the e-tendering portal.
  7. After award, read your assessment summary and keep it for the next bid.

Preparing quality responses is where most of the time goes. Explain Response is an AI agent that works inside Microsoft Word: it reads the tender documents, builds a structure that follows the buyer's questions and drafts a first version from your own references and past bids, which your team then reviews and completes. Your data is hosted in France and never used to train a model. Book a 30-minute demo on a real tender.

Reciba nuestros análisis cada mes

La contratación pública, explicada: tendencias, métodos y novedades del producto.

Contáctenos
Hablemos

Descubra cómo Explain responde a sus licitaciones.

Una demo de 30 minutos sobre sus licitaciones reales, con un experto que conoce su sector.